Milestones
Spring 2022
- Schematic Design of Master Plan assembled by civil engineering firm - Gale Associate, Inc.
Fall 2022
- Cost Estimates finalized
Fall 2022
- Meetings with Northborough and Southborough financial planning boards
- Permit applications submitted to Town of Northborough
- Proposals submitted to each town’s Community Preservation Committees for grant funding.
Winter 2023
- Community outreach to user groups and community
- Procurement process commences - bid materials sent to contractors.
March/April 2023
- Project presented at Northborough and Southborough Town Meetings for approval
May 2023
- Contract & Plans finalized with contractor
Summer 2023
- Demolition of old complex
- Construction begins
Fall 2023
- Construction of Courts, Fields and Track is completed
Winter 2023
- Renovation to amenities building
Spring 2023
- Grounds around stadium are updated
- Project Completion