The Plan

THE GONKPLEX MASTER PLAN

What is included in the "Gonkplex"?

  • Two Turf Fields
  • Track
  • ADA Compliant Stands
  • Press Box
  • Tennis Courts
  • Pickle Ball and Basketball Courts
  • Updated Grounds Around Stadium
  • Amphitheater
  • Updated Concession/Amenities Building

 

Milestones

Spring 2022

Fall 2022

  • Cost Estimates finalized

Fall 2022

  • Meetings with Northborough and Southborough financial planning boards
  • Permit applications submitted to Town of Northborough
  • Proposals submitted to each town’s Community Preservation Committees for grant funding. 

Winter 2023

  • Community outreach to user groups and community
  • Procurement process commences - bid materials sent to contractors. 

March/April 2023

  • Project presented at Northborough and Southborough Town Meetings for approval

May 2023

  • Contract & Plans finalized with contractor

Summer 2023

  • Demolition of old complex
  • Construction begins

Fall 2023

  • Construction of Courts, Fields and Track is completed

Winter 2023

  • Renovation to amenities building

Spring 2023

  • Grounds around stadium are updated
  • Project Completion